Hi,

Is it possible to permenantly suspend a schedulded task?

I have 2 workspaces for 2 different applications. When I switch between them, using the integrated server. All scheduleds tasks are set to run. I can dissable them using the Ebaseadmin. But the next time, I switch to the workspace again, all checkboxes for 'suspend' are cleared.

This is a problem for us because we use a single development db with multiple developers and we want the scheduled tasks that opperate on this data to be run only form our 'staging server'.

Regards,

David
0 x

Jon
Moderator
Moderator
Posts: 1342
Joined: Wed Sep 12, 2007 12:49 pm

#2

Postby Jon » Fri Apr 01, 2016 10:08 am

No, there is no suspend option on the design-side of scheduled tasks, you just have the Schedule Type = None option.

I think this is probably a bug. If you have previously suspended a task in the server admin app, this should be remembered. I'll log it.